Owner City of Edmonton
Contract completed over the summer seasons of 2017 to 2018. This project consisted of resurfacing the roadway and realignment of turning bays at 50 street with a contract value of over 3 million dollars.
Project Scope:
– Removal and disposal of existing concrete.
– Supply and installation of new concrete work.
– Installation of new turning bays including new base.
– Mill and overlay of existing road structure.
– Underground storm realignment underground trench work.
– Topsoil and seed placement.
– Coordinate with Epcor for new Streetlight installation.
– Coordination with high pressure gas line companies.
– Public engagement and traffic accommodation during construction.
– Environmental and tree protection in urban environment.